Library Timeline

By Meredith Stanton Vaselaar

Work is scheduled to begin at the Adrian Branch Library by the end of this week.  Next Monday, February 6, 2017, the asbestos floor tiles will be removed. After that, the renovation will begin in earnest.

At this point in time, I can tell you that the contractor must complete the renovation by June 2, 2017.

We are hoping that the renovation will be completed, and we are able to move back into the Library building, sometime in May 2017.  This, however, is best case scenario.  After the renovation is completed, we will still need to move things back into the library, make sure that everything is in place, and prepare to be re-open.

We will keep everyone updated by putting articles in the newspaper, updating our webpage, our blog, and the fundraising page.

Please stop by the library, or visit our webpage, for more information:  www.plumcreeklibrary.org/adrian